Project Start Date: Wed 10/15/03
Project Finish Date: Fri 2/20/04

Task_Data

IDTask_NameDurationStart_DateFinish_DatePredecessorsResource_Names
1
Acquire Materials
14 daysWed 10/15/03Mon 11/3/03 Structures
2
Manufacture 2 extra satellites
5 wksTue 11/4/03Mon 12/8/031Structures
3
cut out comm antenna
7 daysFri 10/31/03Mon 11/10/03 Structures
4
fix side 4 crossbar
1 wkTue 11/11/03Mon 11/17/033Structures
5
make flight pins
1 wkTue 11/18/03Mon 11/24/034Structures
6
modify kill switches
1 wkTue 11/4/03Mon 11/10/03 Structures
7
assemble solar cell flap/hinge
2 daysFri 10/31/03Mon 11/3/03 Structures
8
wiring book
1.5 wksMon 10/27/03Wed 11/5/03 Structures
9
final assembly
7 daysFri 11/7/03Mon 11/17/03  
10
mass/cg checks
1 dayTue 11/18/03Tue 11/18/039Structures
11
integrated satellite vibration test
1 dayMon 12/8/03Mon 12/8/03 Structures
12
Establish two-way communication with board
0.5 wksWed 10/15/03Fri 10/17/03 Command and Data Handling
13
figure out how interrupt works
2 daysFri 10/17/03Tue 10/21/0312Command and Data Handling
14
define data budget / save rate
2.5 wksTue 10/21/03Thu 11/6/03 Command and Data Handling
15
determine structure of telemetry packet
2.5 wksTue 10/21/03Thu 11/6/03 Command and Data Handling
16
create peek function
2 daysTue 10/21/03Wed 10/22/03 Command and Data Handling
17
define running loop
1 wkFri 10/31/03Thu 11/6/03 Command and Data Handling
18
write main loop
4 wksFri 11/7/03Thu 12/4/0317Command and Data Handling
19
define startup diag sequence
1 wkFri 12/5/03Thu 12/11/0318Command and Data Handling
20
write startup diag sequence
1.5 wksTue 12/30/03Thu 1/8/04 Command and Data Handling
21
define error handling protocol
0.5 wksThu 1/8/04Mon 1/12/0420Command and Data Handling
22
write error handling protocol
1 wkTue 1/13/04Mon 1/19/0421Command and Data Handling
23
CDH architecture complete
1 dayMon 1/19/04Mon 1/19/04  
24
test output of control law
1 wkWed 10/15/03Tue 10/21/03 Attitude Determination & Control Systems
25
determine spacecraft is in correct orientation
2 wksWed 10/22/03Tue 11/4/0324Attitude Determination & Control Systems
26
flip sequence code
2 wksWed 11/5/03Tue 11/18/0325 
27
convert to c
2 wksWed 11/19/03Tue 12/2/0326Attitude Determination & Control Systems
28
integrated adcs software testing
1 wkWed 12/3/03Tue 12/9/0327Attitude Determination & Control Systems
29
adcs/propagator interface definition
1 dayWed 10/15/03Wed 10/15/03 Attitude Determination & Control Systems
30
GG prototype manuf
1 wkWed 10/15/03Tue 10/21/03 Attitude Determination & Control Systems
31
burn wire test
1.6 wksWed 10/22/03Fri 10/31/0330Attitude Determination & Control Systems
32
magnetometer test
2 wksMon 11/3/03Fri 11/14/0331Attitude Determination & Control Systems
33
adcs and propagator integrated test
2 daysThu 12/4/03Fri 12/5/03 Attitude Determination & Control Systems
34
CDH/Power/ADCS Interface Testing (1 orbit)
14 daysFri 1/23/04Wed 2/11/04 Attitude Determination & Control Systems
35
CDH/Power/ADCS interface testing (multiorbit)
7 daysThu 2/12/04Fri 2/20/0434Attitude Determination & Control Systems
36
basic software interface test
1 wkFri 10/24/03Thu 10/30/03 Power
37
order solar cells
1 dayThu 10/30/03Thu 10/30/03 Power
38
orbit power simulation and cell issues
1 wkWed 10/15/03Tue 10/21/03 Power
39
power full test
1 wkFri 10/31/03Thu 11/6/03 Power
40
Testing with CDH
0.5 wksFri 11/7/03Tue 11/11/0339Power,Command and Data Handling
41
Test Power to heater
1 wkTue 11/11/03Tue 11/18/0340Power
42
battery temperature model
1 wkMon 10/27/03Fri 10/31/03 Power
43
power budget
1 wkMon 11/3/03Fri 11/7/0342Power
44
flight pin/kill switch select
1 wkMon 11/10/03Fri 11/14/0343Power
45
Power Integrated test
0 daysThu 10/30/03Thu 10/30/03  
46
temperature sensors
1 wkMon 11/17/03Fri 11/21/0344Power
47
ADCS/Power/Structure burnwire test
1 wkMon 11/24/03Fri 11/28/0346Power
48
Power integrate with CDH
0 daysSat 11/15/03Sat 11/15/03  
49
CDH/Power/ADCS magnetometer test
0.5 wksWed 11/19/03Fri 11/21/03 Power,Attitude Determination &Control Systems
50
torque coils
0.33 wksFri 11/21/03Mon 11/24/03 Power,Attitude Determination &Control Systems,CDH
51
GPS
0.5 wksMon 11/24/03Thu 11/27/0350Power,Science
52
Test voltage Supply to Comm
0.5 wksThu 11/27/03Mon 12/1/0351Power,Communications
53
populate comm board
1.5 wksWed 10/15/03Fri 10/24/03 Communications
54
prototype test of comm board
2 wksFri 10/24/03Fri 11/7/0353Communications
55
Ready for H/W Integration
0 daysSat 11/15/03Sat 11/15/03  
56
test groundstation rotor control
1 wkFri 10/24/03Thu 10/30/03 Communications
57
define comm protocol
1 wkFri 11/7/03Fri 11/14/0354Communications
58
hardware interface test
1 wkFri 11/14/03Fri 11/21/0357Communications
59
Ready for CDH Integrated Test
0 daysMon 12/15/03Mon 12/15/03 Communications
60
fully test CDH (one uplink)
0.5 wksFri 11/21/03Tue 11/25/0358Communications,Command and Data Handling
61
develop and test control software
4 wksWed 11/26/03Tue 12/23/0360Communications
62
fully test CDH (two uplinks)
0.5 wksWed 12/24/03Fri 12/26/0361Communications,Command and Data Handling
63
test antenna and groundstation with onboard
2 wksFri 12/26/03Fri 1/9/0462Communications
64
CDH, onboard and groundstation test
0.5 wksWed 10/15/03Fri 10/17/03 Communications,Command and Data Handling
65
get gps board ready for 2 flight units
3 wksWed 10/15/03Tue 11/4/03 Science
66
CDH interface test
1 wkWed 11/5/03Tue 11/11/0365Science,Command and Data Handling
67
Ready for H/W Integration
0 daysSat 11/15/03Sat 11/15/03 Science
68
propagator test on cold start
1.5 wksWed 11/26/03Fri 12/5/0366Science
69
warm start
1 wkFri 12/5/03Fri 12/12/0368Science
70
CDH send and receive
0.75 wksFri 12/12/03Thu 12/18/0369Science,Command and Data Handling
71
Integrated Testing for Several orbits
1.25 wksThu 12/18/03Fri 12/26/0370Science,Command and Data Handling
72
make one-wire bus
1 wkWed 10/15/03Tue 10/21/03 Thermal
73
basic calculations
1 wkWed 10/22/03Tue 10/28/0372Thermal
74
compare calculations to I-DEAS
1 wkWed 10/29/03Tue 11/4/0373Thermal
75
create full I-DEAS model
20 daysWed 11/5/03Tue 12/2/0374Thermal
76
compare new model with old
1 dayWed 12/3/03Wed 12/3/0375Thermal
77
I-DEAS model of orbit
2 wksWed 10/22/03Tue 11/4/03 Thermal
78
vacuum testing
2 wksWed 11/5/03Tue 11/18/0377Thermal
79
set up vacuum chamber for full test
2 wksWed 11/19/03Tue 12/2/0378Thermal
80
Test with one wire bus
0.5 wksWed 10/29/03Fri 10/31/03 Thermal,Command and Data Handling
81
Ready for Integration
0 daysThu 10/30/03Thu 10/30/03  
82
Test CDH Power with sensors
1.67 daysThu 11/6/03Fri 11/7/03 Thermal,Command and Data Handling,Power
83
Ready to Test
0 daysThu 11/27/03Thu 11/27/03  
84
full model vacuum test
1 wkMon 12/1/03Fri 12/5/03 Thermal
85
correlation of test results with full model
1 dayMon 12/8/03Mon 12/8/0384Thermal
86
CDH, Power Thermal interface testing (one orbit)
1 dayMon 12/1/03Mon 12/1/03 Command and Data Handling,Thermal,Power
87
CDH Power Thermal Interface (multiorbit)
1 dayTue 12/2/03Tue 12/2/0386Command and Data Handling,Thermal,Power